Curtailed solar can charge add-on batteries: what lenders should ask

Writer: Vaultus
Vaultus
Aug 24
4 min read

Updated: 3 days ago

From our archive: we wrote this note after the week shown above, as part of our back catalogue. For anything newer, see the latest posts in this section.


A Ministry of Power letter dated 27 August 2026 lets renewable projects use power curtailed under temporary network access to charge an extra battery at the same site, and sell that stored power to any buyer. The battery sits outside the existing power purchase agreement and needs no objection certificate from the buyer. That creates a new kind of battery cash flow, with no contracted buyer, which lenders will be asked to finance.


The Storage Brief, week of 24 August 2026


What changed

The Ministry of Power issued a clarification on the recommendation of the Ministry of New and Renewable Energy (MNRE), as reported by SolarQuarter and Renewable Watch.


Renewable projects awarded under the standard bidding guidelines may use energy curtailed under temporary general network access (T-GNA) to charge an additional battery at the same site. The battery must be voluntary and outside the existing power purchase or power sale agreement. Developers don't need a no-objection certificate from the procurer. They may sell the stored power through power exchanges or bilateral deals. The letter follows an MNRE memorandum dated 22 July 2026.


Why it matters

Curtailment means a plant is told to back down because the grid can't take its power, and the energy is lost. Plants on temporary network access are the first to be backed down when lines are full, so the losses can be large at congested times of day. The letter turns that lost energy into stock. A battery charged with power that would otherwise be thrown away costs little or nothing to charge, and earns whatever the market pays when it discharges.


Take a solar plant that adds a 20 MWh battery and fills it on curtailed afternoons (an example). If curtailment happens on 100 days a year, that's up to 2,000 MWh a year to sell in the evening, before battery losses (our calculation: 20 MWh × 100 days). Halve the curtailed days and the energy to sell halves too.


Most battery deals lenders see in India today have a contracted buyer: a DISCOM (power distribution company) paying a monthly capacity charge, or a site paying a monthly plan. This one may not. Its revenue depends on how often curtailment happens, how much the battery captures, and the gap between charging cost and evening sale prices. Each of those can shift with new transmission lines, new rules or more batteries chasing the same evening hours. It's a merchant asset, and it needs underwriting as one.


What it means for you

  • Sites: Nothing changes directly. Over time, more batteries selling into evening hours could move exchange prices, which matters if you buy power through open access.

  • Battery makers: Expect enquiries from renewable plant owners for add-on batteries at existing sites. These buyers will ask hard questions about cycle life, because their revenue depends on it.

  • Lenders: Ask for at least a year of curtailment records by time block, the battery's planned dispatch, and a downside case with lower curtailment. Compare that with the steadier profile of contracted battery cash flows.


The number

Zero: the number of no-objection certificates a developer now needs from its existing power buyer to add such a battery. Source: Renewable Watch, 31 August 2026.


What to do now

  1. Lenders: draft a short checklist for merchant batteries: curtailment history, price spread assumptions, and what happens if curtailment falls.

  2. Battery makers: prepare a sizing note for add-on batteries at existing solar plants, with cycle life and warranty terms stated plainly.

  3. Everyone: read the letter itself before acting on press summaries, and check the exact conditions against the Ministry's notified text.


What we don't know yet

  • How much curtailed energy will actually be available once new transmission lines are commissioned.

  • How regulators will treat scheduling and deviation for these add-on batteries.

  • Whether evening exchange prices will hold up as more storage enters the market.


Questions we get asked

Q: Can a solar plant in India sell curtailed power through a battery? A: Yes, under this letter, if the power was curtailed under T-GNA. The plant can store it in an extra battery that isn't part of the existing contract and sell it separately.


Q: Why should a company buying a business battery care about this rule? A: Indirectly. It grows demand for batteries and installers, and shows policy now treats stored energy as having its own market value.


Q: Is a merchant battery project a bad credit risk? A: Not by default. Its risk is different: revenue depends on market conditions rather than a contract, so it needs different terms.


Key facts


Sources


Keep reading





Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.