top of page

Maharashtra's new 4 GWh battery tender writes the cycle clause upfront

Writer: Vaultus
Vaultus
Jun 29
4 min read

Updated: 3 days ago

From our archive: we wrote this note after the week shown above, as part of our back catalogue. For anything newer, see the latest posts in this section.


Four weeks after a tribunal quashed its last battery tender over a cycle clause added after bidding, MSEDCL has floated a new one of the same size: 2,000 MW/4,000 MWh, reported on 3 July 2026. This time the right to use the batteries for at least 6,300 cycles at no extra cost is in the tender from the start, so bidders can price it. Battery makers selling to businesses should take the same lesson: state the use, then price it.


The Storage Brief, week of 29 June 2026


What changed

Renewable Watch reported on 3 July 2026 that MSEDCL, Maharashtra's state DISCOM, has invited bids for 2,000 MW/4,000 MWh of battery storage, split into two equal parts of 1,000 MW/2,000 MWh. Part A is for batteries at MSEDCL and state transmission substations. Part B covers co-located and standalone projects connected to the state transmission network.


Projects are build-own-operate under a battery energy storage purchase agreement: MSEDCL supplies the charging power and calls the discharge. MSEDCL can use the systems for at least 6,300 cycles over the contract at no additional cost. MSEDCL's replies to bidders' pre-bid queries on tender MSEDCL/BESS/Phase-2/26-27/001 confirm a 15-year agreement, say MSEDCL decides how the cycles are used and may schedule more than one a day, and decline to pay for extra cycles. Projects can get up to ₹18 lakh per MWh in central viability gap support. Bids are due on 22 July 2026.


On 5 June, APTEL had set aside MSEDCL's earlier tender of the same size because the 6,300-cycle condition arrived after bids had been priced on about 5,475 cycles.


Why it matters

The fix is simple, and it's the right one. A cycle right that appears after bidding is a free option for the buyer. Written into the tender, the same right becomes an ordinary term, and bidders put a price on it. We expect bids to reflect the extra wear, through a higher capacity charge, larger batteries, or both. Either way, the risk now sits where everyone can see it.


For battery makers selling to hospitals, campuses and factories, this is a template worth copying. Your customer contract should say how many cycles, or how many kWh a day, the site can draw, and what happens beyond that. Your cell supplier's warranty should cover at least that much.


Example: say a maker quotes a campus a contract that allows 1.5 cycles a day for 10 years, while its cells are warranted for 4,000 cycles (illustrative figures). Our calculation: 1.5 × 365 × 10 = 5,475 cycles the customer can call, against 4,000 warranted, a gap of 1,475 cycles the maker carries alone. A lender looking at a pool of such contracts will ask the question APTEL asked: did the seller price what the buyer can demand?


What it means for you

  • Sites: Expect your battery contract to state a daily use limit. A clear limit is a sign the contract has been priced properly.

  • Battery makers: Match three numbers before you quote: cycles the customer can call, cycles your cells are warranted for, and cycles your price assumes.

  • Lenders: In storage tenders and business contracts alike, check that the use the buyer can demand is fixed at signing.


The number

₹720 crore: the most central support this tender could draw, if every project gets the full amount. Source: our calculation, 4,000 MWh × ₹18 lakh per MWh = ₹720 crore.


What to do now

  1. Makers: put your three cycle numbers (contract, warranty, price) side by side for every open quote.

  2. If you supply cells or systems to tender bidders, check their bid assumes 6,300 cycles, not one a day.

  3. Sites: ask your battery maker to show the daily use limit in writing before you sign.


What we don't know yet

  • Whether MSEDCL will resolve an inconsistency bidders flagged in where Part B projects sit.

  • What capacity charges bidders will offer now that the cycle right is priced in.

  • Whether any party seeks to revive the earlier tender's results.


Questions we get asked

Q: Why does the number of battery cycles change the price? A: Each cycle wears the cells a little. More cycles mean earlier replacement or a bigger battery, and the seller has to recover that cost.


Q: Is 6,300 cycles a lot for a battery storage contract? A: It depends on the term. Over this tender's 15 years, 6,300 cycles is about 1.15 a day. Our calculation: 6,300 ÷ 5,475 days ≈ 1.15.


Key facts

  • Document: MSEDCL tender for 2,000 MW/4,000 MWh BESS under the Ministry of Power VGF scheme, as reported by Renewable Watch

  • Issued by: MSEDCL (Maharashtra State Electricity Distribution Company Limited)

  • Date: reported 3 July 2026; bids due 22 July 2026

  • Status: announced (tender open)

  • Applies to: two parts of 1,000 MW/2,000 MWh each, at substations and on the state transmission network; build-own-operate, 15-year agreement, at least 6,300 cycles at no extra cost, central support up to ₹18 lakh per MWh

  • What it means for business batteries: the cycles a buyer can call should be written into the contract before pricing, and matched to the cell warranty.


Sources


Keep reading





Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.