Maharashtra's rooftop tender puts batteries inside a 25-year tariff

Writer: Vaultus
Vaultus
Jun 8
4 min read

Updated: 3 days ago

From our archive: we wrote this note after the week shown above, as part of our back catalogue. For anything newer, see the latest posts in this section.


On 8 June 2026 MAHAPREIT, a Maharashtra government company, invited bids for 100 MW of rooftop solar for MSMEs and other businesses, sold per unit under 25-year fixed tariffs. Half the capacity comes with batteries, and for systems above 100 kW the tender describes two-hour batteries as mandatory under the state's new policy. The site buys power, not equipment, and the developer owns, maintains and replaces the battery.


The Storage Brief, week of 8 June 2026


What changed

MAHAPREIT's request for proposal, dated 8 June 2026, seeks developers for 100 MW of behind-the-meter rooftop solar under the RESCO model, where the developer owns the system and sells power to the site. It's split into four 25 MW categories. For 20 to 100 kW systems, one category adds batteries at 30% of solar capacity for two hours. For 101 to 250 kW systems, one category adds batteries at 50% for two hours, which the RFP calls mandatory for new projects above 100 kW from April 2026.


Buyers are MSMEs and other industrial, commercial or institutional consumers. Each bidder quotes one fixed tariff per kWh for 25 years, with no escalation, covering maintenance and battery replacement. The RFP cites Maharashtra's Renewable Energy and Energy Storage Policy 2025-26 to 2035-36, issued by government resolution on 18 March 2026. Bids close on 23 June.


Why it matters

Here a state body is writing batteries into a pay-per-unit contract for small businesses. The site makes no upfront purchase. The developer carries the battery for 25 years, including any replacement, and has to fold all of that into a single flat tariff. That suits a factory that can't spare capital. It's also a bet by the developer on future cell prices, since the tariff can't rise.


Example: take an MSME in Aurangabad with a 50 kW rooftop in the 20 to 100 kW battery category. Our calculation: 30% of 50 kW is a 15 kW battery, and two hours of it is 30 kWh. The owner never buys that battery. It shows up only inside the per-unit tariff, for 25 years.


The wider effect reaches every rooftop quote in the state. If new systems above 100 kW in Maharashtra must carry batteries, as the RFP says, every quote in that bracket now carries battery cost. The question a CFO asks moves from "is solar cheap?" to "who owns the battery risk for 25 years, and how is that paid for?" MAHAPREIT also keeps a service charge of 3% of the tariff, rising 5% every five years, for metering, billing and collection, so a state body, not the developer, bills and collects from each site.


What it means for you

  • Sites: Planning rooftop solar above 100 kW in Maharashtra? Assume a battery is part of it, and decide whether to own it or pay per unit.

  • Battery makers: The RFP lets bidders qualify on storage experience of at least 0.5 MW/1 MWh, or an agreement with a certified battery provider. That opens a route to supply developers who lack a storage track record.

  • Lenders: A 25-year flat tariff with a battery replacement inside it needs a clear view of cell prices and degradation. Read the payment security terms in the PPA (power purchase agreement) before lending.


The number

50% for two hours: the battery size in the 101 to 250 kW category, so a 200 kW rooftop needs 200 kWh of storage. Source: MAHAPREIT RFP; our calculation, 50% of 200 kW = 100 kW, × 2 hours = 200 kWh.


What to do now

  1. Read section 5.4 of the March 2026 state policy, which the RFP cites for the battery requirement, and check with MSEDCL how it applies to your connection.

  2. If you have a rooftop quote above 100 kW, ask the bidder how battery replacement is priced over the contract life.

  3. Makers: check the RFP's ALMM (Approved List of Models and Manufacturers) requirement for solar modules and cells, and its battery certification terms (BIS or IEC 62619), before teaming with a bidder.


What we don't know yet

  • What tariffs bidders will quote. Financial bids open later.

  • The full payment security terms, which sit in the PPA.

  • How many MSMEs will sign up once tariffs are known.


Questions we get asked

Q: What is the RESCO model for rooftop solar? A: A renewable energy service company owns and maintains the system on your roof and sells you the power at an agreed tariff.


Q: Is a battery mandatory with rooftop solar in Maharashtra? A: The RFP says batteries are mandatory for new behind-the-meter projects above 100 kW from April 2026, and links this to the state policy. Check the notified policy text and your DISCOM's rules for your case.


Key facts


Sources


Keep reading





Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.