Updated 17 November 2026: we read the notified regulation text and added a checklist for owners of 50 MW+ storage, corrected which parts start later, and replaced the footer.
From 1 April 2027, any company that owns 50 MW or more of energy storage must run a full cyber security regime under the Central Electricity Authority's (CEA) new regulations: a named Chief Information Security Officer, an approved policy and crisis plan, internet-isolated controls, records kept in India, a yearly audit and six-hour incident reporting. Smaller business batteries that can export are reached through their suppliers, who must keep monitoring records in India and secure remote access.
The Storage Brief, week of 2 November 2026
What changed
The Central Electricity Authority (Cyber Security in Power Sector) Regulations, 2026 were notified on 31 July 2026 (Gazette of India, Extraordinary, No. 484) under the Electricity Act, 2003. Status: notified; in force from 1 April 2027. They cover:
Generators, captive plants and "organisations having Energy Storage System", where the entity has an installed capacity of 50 MW or more. Entities below 50 MW are "encouraged" to follow CERT-In's 15 baseline controls for small firms.
Transmission and distribution licensees, and the load dispatch centres.
Power exchanges and over-the-counter trading, except the operational technology, vendor and prosumer clauses.
Vendors, defined to include makers and suppliers of inverters, communication modules, monitoring and energy management software for small grid-connected solar and storage owned by consumers.
Six clauses start only on dates CEA will set by order with central approval: 5(9), a round-the-clock Information Security Division in India; 5(24), ISO/IEC 27001 or a Technical Criteria Certificate; 5(33), designated courses for all operating staff, including vendor staff; 5(39) and 6(7), buying IT and control equipment only from trusted sources; and 6(2), the firewall where the control system meets the power system's communication network. Our earlier note listed these loosely. This is the exact list.
If you own a 50 MW+ storage award: your 1 April 2027 checklist
Many new storage owners are EPC or infrastructure firms. The rules apply to their "existing as well as upcoming infrastructure", so a project being built now should be designed to them. This is what the text asks for from day one, in the order most owners find hardest:
People
A Chief Information Security Officer and an alternate: regular senior employees, Indian citizens and residents, with an engineering degree and at least 15 years in power or IT. The CISO reports to the head of the entity, holds the post for at least three years, does only cyber work and trains five days a year.
Their contact details published and sent to CSIRT-Power, the power sector's incident team.
Documents
A Cyber Security Policy, aligned to the business continuity plan, approved and reviewed each year by the head or the board.
A Cyber Crisis Management Plan, prepared with CSIRT-Power, vetted by CERT-In, and approved and reviewed each year by the head or the board.
An Incident Response and Recovery Plan, reviewed every six months.
A cyber asset register and a register of critical systems, plus a risk assessment and mitigation plan updated every six months.
A backup policy: backups no older than a month, kept separately, with restores tested.
A retention policy: logs kept 180 days, incident logs a year, factory and site test reports for the asset's life.
The control system
Control systems physically isolated from the internet and from office IT. Where a link to office IT can't be avoided, a hardened separation approved by the head or board and monitored. The text gives no such exception for the internet.
Control and real-time exchange over a dedicated channel that stays inside India.
Remote operation only from within India, with prior approval of the head or board. Remote access only for troubleshooting or emergencies, approved and logged.
Sensitive records, including cloud copies and history, encrypted and held in India.
Clocks synchronised to a terrestrial or Indian satellite time source independent of the internet.
Buying and commissioning
Factory and site acceptance tests that include cyber security tests, written into procurement.
Vulnerability assessment and penetration testing before any new critical system is commissioned, and its details sent to CSIRT-Power within 30 days.
Vendor contracts that carry the cyber requirements and a non-disclosure agreement, a bill of materials for software, and patches for the contract period or the system's useful life, whichever is later. Control-system patches must be digitally signed by the maker or checked for authenticity.
Audit, drills and reporting
A yearly cyber security audit by a CERT-In empanelled auditor, between 9 and 15 months apart, never three in a row by the same firm. Critical and high findings fixed within a month of the report.
An annual self-audit, and awareness sessions and mock drills every six months.
Incidents reported to CSIRT-Power and CERT-In within six hours, or 24 hours for sabotage of a critical system.
The audit and crisis plan take the longest, because they depend on outside parties. From 17 November 2026 there are 135 days to 1 April 2027 (our calculation).
Why it matters
A battery plant is a set of computers that move megawatts. From April 2027 its security is a legal duty, not a contract preference. The Ministry of Power's Chief Information Security Officer can, with CEA's approval, appoint a third-party auditor at the entity's cost, and can recommend proceedings under the IT Act or a petition to the regulator under section 142 of the Electricity Act, which carries penalties.
The patch clause moves the most money. Vendors must keep patches available to a covered owner for the contract period or the system's useful life, whichever is later. An example: a battery commissioned in April 2027 on a 10-year contract needs patches until April 2037. If the supplier supports the software only for a 5-year warranty, half the term has no patch cover (our calculation: 5 of 10 years).
For smaller business batteries
For small grid-connected solar and storage owned by a consumer who can also export ("prosumer" in the rules), the vendor must keep monitoring and control servers, cloud copies and history encrypted in India, and use mutually authenticated, encrypted channels for remote access. For systems already installed, CEA will set the start date by order.
What to ask your supplier
Where are the monitoring servers and backups hosted, and in which country?
Who can log in remotely, how is access approved, and is it logged?
For how many years will you supply signed patches? Write it to the system's useful life.
Will you give us a software bill of materials and your end-of-support dates?
How fast will you tell us about an incident? A covered owner has six hours.
What we don't know yet
The dates for the six clauses that start by separate order.
Whether the 50 MW test counts an owner's total storage across projects. The text reads "where such entities have an installed capacity of 50 MW or more", which points to the entity, not each project. Check with counsel.
Whether a behind-the-meter battery that never exports counts as a prosumer's resource under the vendor clause.
Questions people ask
Q: Do the CEA cyber rules apply to a factory or office battery? A: The full rules apply to entities with 50 MW or more of storage. Smaller systems owned by consumers who can export are reached through their vendors, who must keep records in India and secure remote access.
Q: What does a 50 MW battery storage owner need for CEA cyber compliance by April 2027? A: A qualified CISO and alternate, a board-approved cyber policy, a crisis plan vetted by CERT-In, isolated control systems, records in India, a yearly audit by a CERT-In empanelled auditor and six-hour incident reporting.
Q: When do the CEA cyber security rules start? A: On 1 April 2027. Six clauses start on dates CEA will set by order.
Key facts
Document: Central Electricity Authority (Cyber Security in Power Sector) Regulations, 2026
Issued by: Central Electricity Authority, F. No. CEA-HY-91-19/8/2024-Cyber Security Division
Date: notified 31 July 2026 (Gazette No. 484)
Status: notified; in force from 1 April 2027; six clauses on dates to be set
Applies to: entities with 50 MW or more of generation, captive or storage capacity; licensees and load dispatch centres; exchanges; vendors, including for consumer-owned solar and storage
Sources
Central Electricity Authority (Cyber Security in Power Sector) Regulations, 2026. Gazette of India, Extraordinary, No. 484, 31 July 2026. Listed on CEA's cyber security regulations page.
Keep reading
Same date, different rule: CEA battery safety rules: what changes for storage from April 2027
All the dates: Battery rules calendar for Indian businesses: key dates to April 2027
For grid storage owners: CEA battery standards: 80% health at year 10 is the new floor
Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.