What CERC's 2025-26 rules mean for batteries

Updated: 3 days ago
CERC's 2025-26 changes are about batteries on the inter-state grid, not behind a factory meter. Grid-charged batteries are losing their transmission charge waiver in steps: 75% if commissioned from July 2025, 50% from July 2026, 25% from July 2027, nothing after June 2028. Batteries charged from solar or wind at the same substation keep a full 12-year waiver if commissioned by 30 June 2028, and a May 2026 draft would require two hours of storage for storage seeking new grid connections. None of this changes a site's bill directly, but it shapes what grid storage costs and earns.
The Storage Brief, market note, updated 31 October 2026. Next update due in the first week of December 2026.
What changed, by date
28 Oct 2026 (Proposed): Pumped storage proposed for the high-price day-ahead market, already open to batteries. Hearing 19 Nov. CERC, 13/SM/2026
26 Oct 2026 (Draft): Solar and wind delayed by late transmission keep their graded waiver if contracts are signed by 31 March 2027. Comments by 27 Nov. CERC
21 Sep 2026 (Draft): Grid code: standalone storage trial runs of at least 50 MW; instalments for 250 MW and above. Comments by 2 Nov. CERC
25 Aug 2026 (In force (31 Aug 2026)): Deviation rules: standalone storage's pre-trial power paid at the normal rate, capped at ₹2/kWh; future wind and solar settle like other generators. CERC
31 Jul 2026 (Draft (hearing set for 28 Sep)): Transmission charges: co-located battery waiver counted cycle by cycle; green day-ahead purchases count towards the 51% green charging test. CERC
20 May 2026 (Draft (comments closed 29 Jun)): Connectivity: storage must discharge at least twice its connectivity quantum in MWh, so two hours. CERC
20 Mar 2026 (Notified): Tariff: 15-year useful life for lithium-ion storage at CERC-regulated plants (gazette 10 Apr). CERC
31 Aug 2025 (In force): Connectivity: storage of 50 MW and above can take non-solar-hour access (gazette 9 Sep 2025). CERC
26 Jun 2025 (In force): Transmission charges: battery waiver schedule, after a June 2025 Ministry of Power order (gazette 2 Jul). CERC
Why it matters for a battery
Start with the waiver, because it moves the most money. Transmission charges fall on the buyer, so the waiver lowers the delivered cost of stored energy. Under the Fourth Amendment, a grid-charged battery gets 100% for 12 years if commissioned by 30 June 2025, then 75%, 50% and 25% in each following year, and nothing after 30 June 2028. A battery charged from solar or wind at its substation gets 100% for 12 years if commissioned by 30 June 2028, and may draw up to 10% of its yearly charging from the grid in a contingency.
Take a grid-charged battery commissioned in November 2026 (an example). It falls in the 1 July 2026 to 30 June 2027 band, so its buyers get half the transmission charge waived for 12 years. A year's delay cuts that to a quarter.
The 2026 drafts push towards longer storage. A 50 MW connection would need at least 100 MWh (our calculation: 50 MW × 2). The Fifth Amendment draft would give the full co-located waiver only to cycles charged from renewables at the substation.
Deviation rules raise the value of holding schedule. The 2024 regulations, in force since 16 September 2024, tie the deviation rate to exchange prices. Now wind and solar bid from 1 January 2027, or commissioned from 1 January 2029 if not bid, will pay like any other seller. Storage at the plant cuts that cost.
Ancillary services are open to storage but unchanged. The 2022 regulations let storage, alone or aggregated, provide secondary and tertiary reserves (SRAS and TRAS) if it meets communication and metering rules, with at least 1 MW of response for secondary reserve. We found no 2025-26 amendment.
Market coupling, ordered for the day-ahead market in July 2025, is still a draft rule. For a business site, all this works at one remove: through green open access prices and competition for cells and installers.
What it means for you
If you run a site: Nothing changes behind your meter. If you buy green power through open access, ask how the waiver step-down affects new contracts.
If you make or install batteries: If the drafts become final, grid connections will need two-hour systems and the waiver will favour co-location with solar. Plan cycle life and warranties for that duty.
If you lend or lease: Model the waiver band from the expected commissioning date, and test a one-year slip. Check whether the 51% green charging test is met each year.
The number to know
50%: the share of inter-state transmission charges waived for 12 years for a grid-charged battery commissioned between 1 July 2026 and 30 June 2027. Source: CERC Sharing Regulations, Fourth Amendment, 2025.
What to watch next
2 November 2026: comments close on the grid code draft; hearing on 4 November.
19 November 2026: CERC hearing on pumped storage in the high-price market.
27 November 2026: comments close on the supplementary transmission charges draft.
1 July 2027: grid-charged batteries commissioned from this date get a 25% waiver.
What we don't know yet
Whether the two-hour minimum survives in the final rules.
How NLDC will count charging cycle by cycle.
Whether the Ministry of Power extends the battery waiver again, as it has before.
Questions people ask
Q: Do batteries in India still get the ISTS charge waiver? A: Yes, on a falling scale: 50% for grid-charged batteries commissioned July 2026 to June 2027, and 100% for those charged from co-located solar or wind and commissioned by 30 June 2028.
Q: Can batteries earn from ancillary services in India? A: Yes. CERC's 2022 rules let storage, standalone or aggregated, offer secondary and tertiary reserves if it meets technical conditions.
Q: Do these CERC rules apply to my factory's battery? A: Not directly. A battery behind your meter follows your state commission's rules, so check with your DISCOM.
Sources
Sharing of Inter-State Transmission Charges and Losses (Fourth Amendment) Regulations, 2025. CERC, 26 June 2025.
Draft Sharing (Fifth Amendment) Regulations, 2026. CERC, 31 July 2026.
Supplementary draft notification, Sharing (Fifth Amendment). CERC, 26 October 2026.
Draft Connectivity and GNA (Fourth Amendment) Regulations, 2026. CERC, 20 May 2026.
Connectivity and GNA (Third Amendment) Regulations, 2025. CERC, 31 August 2025.
Deviation Settlement Mechanism (Third Amendment) Regulations, 2026. CERC, 25 August 2026.
Ancillary Services Regulations, 2022. CERC, 2022.
MoP extends ISTS charges waiver for ESS projects. Renewable Watch (reported), 11 June 2025.
Keep reading
Next market note: Battery cells in 2026: LFP now, sodium-ion next. Should you wait?
Previous market note: Open access and grid access in 2026: what business buyers face
Check your site: Which battery and diesel rules apply to my site? A quick check for India
Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.