GRAP Stage III is in force in NCR. Can your generator still run?

Writer: Vaultus
Vaultus
3 days ago
4 min read

Yes, if it meets CAQM's generator rules. No, if it doesn't. Stage III, in force across NCR since 6 November 2026, adds no new generator rule of its own. The rules that decide which sets may run have applied since Stage I began on 21 October, and they stay until Stage I is lifted.


The Storage Brief, 15 November 2026


What changed

  • 6 Nov 2026 (in force): CAQM invoked Stage III ('Severe', AQI 401 to 450) across NCR, on top of Stages I and II, as a precaution against forecast severe air. Source

  • 2 Nov 2026 (in force): Stage II invoked after Delhi's AQI reached 324. Source

  • 21 Oct 2026 (in force): Stage I invoked. This is the stage that carries the generator rules. Source

  • 29 Sep 2026 (notified): CAQM's revised GRAP schedule moved the generator rules into Stage I. Our earlier brief


Why it matters

Several news reports this month said generators "cannot be used" under Stage III. The CAQM order says something narrower. It lists no generator action in Stage II or Stage III. Generators are covered by two Stage I actions, and the order keeps Stage I in force alongside the later stages.


Action 17 says diesel generator sets should not be used as a regular source of power. Action 18 enforces CAQM's Direction No. 76 of 29 September 2023, which sets which sets may run by size and fuel. Gas sets, and sets up to 800 kW built to the 2022 emission standard, have no restriction. Older diesel sets of 41 kW to 800 kW need a dual-fuel kit or a certified emission control retrofit. A set that meets none of the conditions may run only at listed emergency services, such as hospitals, lifts, water pumping and telecom.


So the question for a site isn't which stage Delhi is in. It's what your generator is. And the window matters as much as the stage. From 21 October, no generator is meant to be a site's regular source of power until Stage I is lifted. Last season, CAQM's order revoking Stage I came on 16 March 2026.


What it means for you

  • Sites: Check the generator's nameplate and emission certificate: fuel, size in kW, the standard it was built to, and whether it has a dual-fuel kit or certified retrofit. An older diesel-only set with none of these, at a site that isn't an emergency service, should stay off while GRAP is on.

  • Battery makers: Expect NCR enquiries from sites whose older sets fail this test. Size for the loads that must stay on through short cuts, not the whole building.

  • Lenders: For an NCR site, the generator's compliance is now part of the credit story every winter. Ask for its emission certificate in the site file.


The number

146 days. That is how long Stage I would run if this season matches the last one (an example: our calculation, 21 October 2026 to 16 March 2027 = 10 + 30 + 31 + 31 + 28 + 16 = 146 days, or 40% of the year). For those days, the rules say a generator should not be the site's regular source of power.


What to do now

  1. Photograph the generator nameplate and emission certificate, and check them against the size table in our earlier brief.

  2. If the set doesn't comply, price the three routes side by side: a certified retrofit, a dual-fuel kit (which needs a gas supply), or a battery for the critical loads with the generator kept for long cuts where the rules allow.

  3. Pull last winter's diesel purchase records and work out how many hours the set really ran. That number, more than any rule, decides whether a battery pays.


What we don't know yet

  • How long Stage III will last. CAQM decides on forecasts and revokes stages as air improves.

  • Whether CAQM will tighten Direction No. 76 again for older sets.


Questions we get asked

Can I run my diesel generator during GRAP Stage III in Delhi NCR?


Stage III adds no generator rule. A set that meets Direction No. 76 may run, though the Stage I action says no generator should be a regular source of power. A set that doesn't comply may run only at listed emergency services.


Which generators are allowed in NCR during GRAP?


Gas sets of any size; sets up to 800 kW built to the 2022 emission standard; older 41 kW to 800 kW diesel sets with a dual-fuel kit or certified retrofit; sets of 800 kW and above with a compliant emission control system; and 19 kW to 41 kW sets in dual-fuel mode. Portable sets below 19 kW are not generally permitted.


Does GRAP restrict batteries?


No. GRAP's generator actions cover fuel-burning sets. Batteries have their own safety rules from the Central Electricity Authority, covered in our brief on the CEA safety rules.


Key facts

  • Document: Order invoking Stage III of GRAP in Delhi-NCR

  • Issued by: Commission for Air Quality Management (Sub-Committee on GRAP)

  • Date: 6 November 2026

  • Status: In force

  • Applies to: The entire NCR

  • Takes effect: Immediately, in addition to Stages I and II

  • What it means for business batteries: No new generator rule. The Stage I generator actions and Direction No. 76 continue to decide which sets may run.


Sources


Keep reading


Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.