Open access and grid access in 2026: what business buyers face

Updated: 3 days ago
From our archive: we wrote this note after the week shown above, as part of our back catalogue. For anything newer, see the latest posts in this section.
A business with a contract demand of 100 kW or more can buy green power through open access and bank surplus units within the month, and we found no change to those central terms in 2025-26. What moved is the cost around them: inter-state transmission charges are returning in 25% steps, states set surcharges their own way, and the government told Parliament that 8,133 GWh of solar power was curtailed in April to June 2026. If you buy all your power from your DISCOM, none of this changes your bill directly.
The Storage Brief, market note, updated 31 October 2026. Next update due in the first week of December 2026.
What changed, by date
27 Aug 2026 (reported): Ministry of Power letter lets renewable plants charge an extra on-site battery with power curtailed under temporary network access (T-GNA) and sell it to any buyer. Swarajya
28 Jul 2026 (reported): Government tells Parliament 8,133 GWh of solar was curtailed in April to June 2026. Deccan Chronicle
1 Jul 2026 (in force): Power from new solar and wind plants carries 50% of inter-state transmission (ISTS) charges, up from 25%. MoP orders
8 May 2026 (reported): Supreme Court ruling (2026 INSC 464), reported this day: Indian Railways must pay cross-subsidy surcharge and additional surcharge on open access power. Verdictum
30 Mar 2026 (reported): Ministry of Power says CTUIL holds renewable connectivity applications "beyond 500 GW", still under consideration. PIB
19 Mar 2026 (notified): Delhi phases additional surcharge down to zero within four years of open access being granted. DERC
13 Mar 2026 (in force): Electricity (Amendment) Rules 2026 on captive and group captive power take effect. Our explainer
9 Oct 2025 (draft): Draft Electricity (Amendment) Bill 2025 would end cross-subsidies paid by manufacturing, railways and metros within five years. PRS
19 Sep 2025 (notified): Electricity (Amendment) Rules 2025 let a consumer own, lease or operate storage, and let the owner lease out its capacity. Gazette, via CERC
10 Jun 2025 (in force): Co-located batteries commissioned by 30 June 2028 get a 100% ISTS waiver if their power is used outside the state. MoP orders
Why it matters for a battery
This matters if you buy, or plan to buy, open access power at 100 kW or more, run captive solar, or own a battery. It doesn't if you buy all your power from the DISCOM. Then your tariff order, time-of-day rates and demand charges decide what a battery is worth.
For open access buyers, banking works like a battery on the grid. The 2022 rules make states allow banking at least monthly, of at least 30% of what a consumer takes from the DISCOM, with unused credit lapsing at month end. States set the price: Gujarat set an interim rate of ₹1.50 a unit from 30 March 2026, to apply up to 30 June 2026 or until the commission notified a new charge; check the current rate. Take a factory (an example) that draws 3,00,000 kWh a month and banks 30% of that at ₹1.50. Our calculation: 90,000 kWh × ₹1.50 = ₹1.35 lakh a month. A site battery that stores and returns a unit for less than ₹1.50, losses included, beats banking on that unit.
Surcharges set the gap between open access and DISCOM power. Under the green rules, cross-subsidy surcharge on renewable power can't rise more than 50% above its first-year level for 12 years, and additional surcharge doesn't apply if the consumer pays fixed charges. Other open access still pays it, and states differ: ₹0.76 a unit in Gujarat for April to September 2026, Mercom reported; ₹1.37 in Haryana for late 2025-26, SolarQuarter reported. Captive users skip both.
Inter-state green power costs more each year. ISTS charges fall on the drawing side, not the generator, the MNRE told the Rajya Sabha on 17 March 2026. Power from plants commissioned after June 2025 carries 25%, 50%, 75%, then 100% from July 2028. Power from co-located batteries charged from the plant and commissioned by June 2028 carries none for 12 years when it goes to another state. For now, storage-backed green power crosses state lines more cheaply than plain solar.
The wires are the bottleneck. Ember found on 19 May 2026 that about a quarter of transmission projects nationwide face delays of a year or more. The August letter turns curtailed solar into stored power that plant owners can sell in the evening.
Last, the September 2025 rules give a consumer-owned site battery the consumer's legal status and let its owner lease the capacity to any consumer. A leased site battery now has a clear basis in central rules.
What it means for you
If you run a site: On open access, price a battery against your state's banking charge. On a DISCOM tariff, look at time-of-day rates and demand charges instead.
If you make or install batteries: Target open access and captive solar buyers where banking costs are rising. Quote a cost per unit stored and returned.
If you lend or lease: Site battery leases now rest on central rules. Plant batteries charged with curtailed power earn merchant revenue: underwrite them that way.
The number to know
50%: the share of inter-state transmission charges payable for 25 years on power from a solar or wind plant commissioned between 1 July 2026 and 30 June 2027. Source: Ministry of Power order of 23 November 2021.
What to watch next
30 June 2027: last day for the 50% band. Power from solar and wind commissioned after it carries 75% of ISTS charges.
30 June 2028: last day for co-located batteries to get the full ISTS waiver. Power from new solar and wind carries full charges from 1 July.
Additional surcharge orders for October 2026 to March 2027 in states that reset it twice a year, such as Gujarat.
Whether the Electricity (Amendment) Bill is introduced in Parliament's next session.
What we don't know yet
The text of the 27 August letter. We couldn't find it on the ministry's website; details come from press reports.
Whether curtailment eased after June. The 8,133 GWh figure covers one quarter.
Whether the ministry will extend the ISTS waiver for solar and wind, as it did for co-located storage in June 2025.
Questions people ask
Q: Can a business with a 150 kW load buy green power through open access? A: Yes. The 2022 rules set the threshold at 100 kW of contract demand or sanctioned load, with no limit for captive users. Check your state's charges with its nodal agency.
Q: Does the ISTS waiver phase-out change my bill if I buy only from the DISCOM? A: Not directly. Your state commission's tariff order sets your bill.
Q: Is a battery better than banking for open access solar? A: Compare your state's charge per banked unit, and its time windows, with the battery's all-in cost per unit stored and returned.
Sources
Electricity (Promoting Renewable Energy Through Green Energy Open Access) Rules, 2022. Ministry of Power, Gazette G.S.R. 418(E), 6 June 2022 (copy hosted by MERC).
Orders on waiver of inter-state transmission charges, 2018 to 2025. Ministry of Power, including orders of 23 November 2021 and 10 June 2025.
Electricity (Amendment) Rules, 2025. Ministry of Power, Gazette G.S.R. 688(E), 19 September 2025.
Rajya Sabha reply on waiver of ISTS charges for renewable energy projects. PIB (MNRE), 17 March 2026.
Impact of increasing renewable energy penetration on grid stability. PIB (Ministry of Power), 30 March 2026.
DERC (Terms and Conditions for Open Access) (Second Amendment) Regulations, 2026. DERC, 19 March 2026.
India holds back 8,133 GWh of solar power in April-June quarter owing to transmission constraints. Deccan Chronicle, 28 July 2026.
Power ministry lets green energy firms bottle up wasted electricity in batteries and sell it. Swarajya, 29 August 2026.
Keep reading
Next market note: What CERC's 2025-26 rules mean for batteries
Previous market note: Bilateral deals, exchanges and traders: how power is bought in India
Check your site: Which battery and diesel rules apply to my site? A quick check for India
Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.