CERC's draft storage tariff norms: what battery lenders should check

Writer: Vaultus
Vaultus
Dec 1, 2025
4 min read

Updated: 3 days ago

From our archive: we wrote this note after the week shown above, as part of our back catalogue. For anything newer, see the latest posts in this section.


On 1 December 2025 the Central Electricity Regulatory Commission (CERC) issued draft rules that would let storage at central power plants and inter-state transmission assets earn a regulated tariff. The draft writes down performance norms for batteries: 85% round-trip efficiency, 90% availability and a 12-year useful life. It doesn't cover a battery at a hospital or factory, but it gives lenders a public, regulator-set benchmark to test business battery proposals against.


The Storage Brief, week of 1 December 2025


What changed

CERC issued the draft Central Electricity Regulatory Commission (Terms and Conditions of Tariff) (Second Amendment) Regulations, 2025 on 1 December 2025, and Down To Earth reported on it the next day. It amends the 2024 tariff regulations to cover integrated energy storage at coal, lignite or gas stations and in the inter-state transmission system. Storage costs would be recovered through supplementary fixed and energy charges. Gains from storage services, after costs, would be split 50:50 between the generator and beneficiaries, and beneficiaries get first right to discharge. Comments were first invited until the end of December 2025, and CERC's draft regulations page shows the last date later extended to 31 January 2026. This is a draft. It isn't a final rule yet.


Why it matters

Most of the draft is about how a central generator recovers the cost of a battery it adds to its plant. The useful part for everyone else is the set of numbers. The draft proposes 85% round-trip efficiency, 90% availability, 5% auxiliary consumption, operating and maintenance expenses at 2% of capital cost, and a 12-year useful life for battery storage, over which its cost is depreciated. It also lets storage charge from the host plant, other generators, the grid or the market.


Here's why a lender should care. Credit for a business battery hangs on two questions. Will the system perform? And will it last as long as the loan? Today the answer to both usually comes from the maker's datasheet. A regulator-proposed norm is a neutral reference point.


Take an example: a proposal for a ₹1 crore battery at a factory. At the draft's norms, 1,000 kWh put in gives about 850 kWh back (our calculation: 1,000 × 85% = 850), and upkeep runs about ₹2 lakh a year (our calculation: 2% of ₹1 crore = ₹2 lakh). If the quote claims far better efficiency, or far lower upkeep, ask why. If the loan runs longer than the 12-year useful life a regulator thinks sensible, ask what happens to the system in the later years. The draft doesn't bind private contracts. It does make the conversation more concrete.


What it means for you

  • Sites: Nothing in this draft applies to your meter. It's useful context when a maker quotes efficiency or life figures.

  • Battery makers: Expect buyers and lenders to compare your performance claims with these norms. Be ready to explain any gap.

  • Lenders: Use 85% efficiency, 90% availability and a 12-year life as a sense check on the cash flows in a proposal.


The number

12 years: the useful life the draft proposes for battery storage, which on a straight line writes off about 8.3% of the asset's value a year. Source: CERC draft, 1 December 2025. Our calculation: 100 ÷ 12 ≈ 8.3.


What to do now

  1. Pull the efficiency, availability and life figures from the last three battery proposals you saw.

  2. Mark any figure better than the draft norms and ask the maker for the basis.

  3. Check that loan or lease tenors on battery deals end before the asset's stated life does.


What we don't know yet

  • What changes CERC will make after the comments, and when it will notify final rules.

  • Whether state commissions will borrow these norms for storage at the distribution level.

  • How far real-world battery performance in Indian conditions matches the proposed norms.


Questions we get asked

Q: Can a factory sell stored battery power to the grid under CERC's new rules? A: No. The draft covers storage at central generating stations and inter-state transmission assets whose tariffs CERC sets. Rules for consumers are set by state commissions and DISCOMs (distribution companies).


Q: Does CERC say a battery lasts 12 years? A: Only for tariff purposes. The draft proposes a 12-year useful life for battery storage, which sets how its cost is spread in tariffs. Actual life depends on chemistry, use, temperature and maintenance, and should be set in the supply contract.


Key facts

  • Document: Draft CERC (Terms and Conditions of Tariff) (Second Amendment) Regulations, 2025

  • Issued by: Central Electricity Regulatory Commission (CERC)

  • Date: 1 December 2025

  • Status: draft (comments first invited until the end of December 2025, later extended to 31 January 2026)

  • Applies to: integrated energy storage at coal, lignite or gas stations and in the inter-state transmission system

  • What it means for business batteries: no direct effect on site batteries, but its norms (85% efficiency, 90% availability, 12-year useful life) give lenders a benchmark.


Sources


Keep reading





Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.