Uttar Pradesh: battery, diesel and solar rules for business sites

Writer: Vaultus
Vaultus
Oct 21
7 min read

Updated: 16 hours ago

Updated 17 November 2026: added a section for Noida, Greater Noida and Ghaziabad sites, with this winter's GRAP stages, the generator size table, UP's 75% billable demand rule and a worked generator-hours example.


A business site in Uttar Pradesh faces four state-specific rules on power, diesel and solar. For a site in Noida, Greater Noida or Ghaziabad, two matter most this winter. GRAP's generator rules have applied across NCR since 21 October 2026, and UPERC's tariff order of 2 July 2026 gives commercial sites on HV-1 no time-of-day rate, so their battery case rests on diesel saved and fixed charges, not on shifting load.


The Storage Brief, state guide, updated 17 November 2026


The rules at a glance

  • UPERC tariff order, FY 2026-27 (in force). The order sets rates for the five state DISCOMs (PVVNL, MVVNL, DVVNL, PuVVNL, KESCo). PVVNL serves Ghaziabad and Gautam Buddh Nagar among its 14 districts. Parts of Greater Noida are supplied by a separate licensee, Noida Power Company Limited, under its own schedule; we did not open it, so check your bill.

  • GRAP in UP's NCR districts (in force). The winter air plan covers the eight UP districts in the NCR and curbs diesel generators from Stage I.

  • UP Solar Energy Policy 2022 (policy). The policy waives electricity duty on solar for ten years, captive included.

  • Rooftop net billing (policy). The 2022 policy says business users get net billing, with rooftops of up to 2 MW, under UPERC's 2019 rooftop regulations. We could not open those regulations, so check current terms with your DISCOM.


Noida, Greater Noida and Ghaziabad: this winter

GRAP covers all of NCR, including Gautam Buddh Nagar (Noida and Greater Noida), Ghaziabad, Meerut, Bulandshahr, Baghpat, Hapur, Shamli and Muzaffarnagar. Lucknow, Kanpur and Varanasi are outside it.


This season so far, from CAQM's orders:


  • 21 Oct 2026 (in force): Stage I invoked across NCR. It carries the generator rules.

  • 2 Nov 2026 (in force): Stage II added.

  • 6 Nov 2026 (in force): Stage III added across the entire NCR, at a Delhi AQI of 382 for that day, CAQM's order says. Stages II and III add no generator action.


Stage I's Action 17 says diesel generator sets should not be used as a regular source of power. Action 18 enforces CAQM's Direction No. 76 of 29 September 2023 across industrial, commercial and residential sites. The revised schedule of 29 September 2026 sets out which sets may run:


  • Gas sets of any size (LPG, natural gas, biogas, propane, butane): no restrictions.

  • Sets up to 800 kW (1,000 kVA) built to the 2022 emission standard (GSR 804(E)): no restrictions.

  • Older sets of 800 kW and above: allowed with an emission control system that meets the prescribed standards.

  • Older sets of 41 kW to under 800 kW: allowed in dual-fuel mode or with emission control devices retrofitted through certified agencies.

  • Older sets of 19 kW to under 41 kW: allowed in dual-fuel mode. Sets not in dual-fuel mode only because there is no gas supply may run only for emergency services.

  • Portable sets below 19 kW: not generally permitted.


The emergency services are lifts and escalators, hospitals and health care, railways, metro, airports and inter-state bus terminals, sewage treatment, water pumping, national security projects, and telecom and IT services. District magistrates of NCR states are among the agencies named to enforce the schedule.


Last season, Stage I was revoked on 16 March 2026. If this season runs as long, that is 146 days of Stage I (an example: our calculation, 21 October 2026 to 16 March 2027). For our longer explainer, see GRAP Stage III and your generator.


Your electricity bill

The FY 2026-27 rate schedule keeps last year's time-of-day bands for urban LMV-6 (small and medium industry) and HV-2 (large industry):


  • April to September: 15% off from 05:00 to 10:00, 15% extra from 19:00 to 03:00.

  • October to March: 15% extra from 17:00 to 23:00, 15% off from 23:00 to 05:00.


HV-2 at up to 11 kV pays ₹300 per kVA a month and ₹7.10 per kVAh.


HV-1 covers non-industrial bulk users of 75 kW and above. At 11 kV, commercial users and private institutions (HV-1 a) pay ₹430 per kVA a month plus ₹8.32 per kVAh; public institutions, registered societies and residential townships (HV-1 b) pay ₹380 and ₹7.70. The rate is the same at every hour. The 2023 national rule asked states to bring in time-of-day rates for business users above 10 kW; UP's schedule still has none for HV-1 or LMV-2.


How the fixed charge is billed matters. Under the order's general provisions, billable demand is the higher of the maximum demand recorded by the meter and 75% of contracted demand. Demand above the contract is billed at 200% of the normal rate, on top of the normal charge.


Take an HV-1 office campus in Noida at 11 kV with a 600 kVA contract, 500 kVA recorded maximum demand and 1,00,000 kVAh a month (an example). The floor is 450 kVA, so you are billed on 500. The fixed part is ₹2,15,000 and the energy part ₹8,32,000, so fixed charges are about 20.5% of the base bill (our calculation: 500 × ₹430; 1,00,000 × ₹8.32; ₹2,15,000 ÷ ₹10,47,000). A battery that trims 50 kVA off the peak saves ₹21,500 a month (our calculation: 50 × ₹430). Trimming further saves nothing until you also cut the contract, because the bill cannot fall below 450 kVA (our calculation: 75% × 600).


Diesel backup

We found no UPERC timeline under the national diesel backup rule, Rule 10(6).


Price your generator hour on your own invoice. Delhi's pump diesel was ₹95.20 a litre on 16 November 2026 (PPAC); UP pump prices differ a little through state tax. At 3 to 3.5 units a litre, that is ₹27.20 to ₹31.73 a unit in fuel (our calculation: 95.20 ÷ 3.5; 95.20 ÷ 3). Grid power at the HV-1 a rate, stored in a battery with 85% round trip, costs about ₹9.79 a unit (our calculation: ₹8.32 ÷ 0.85).


Take a Greater Noida office whose generator carries 200 kW through 350 hours of cuts a year that a battery could cover, at 3.2 units a litre (an example). It burns about 62.5 litres an hour, ₹5,950. Recharging a battery for the same hour costs about ₹1,958. The gap is about ₹3,992 an hour, or about ₹14 lakh a year (our calculation: 200 ÷ 3.2 × ₹95.20; 200 × ₹8.32 ÷ 0.85; 350 × ₹3,992). At 50 such hours, it is about ₹2 lakh, and keeping the generator is the better answer.


Solar and storage

The 2022 policy's capital subsidy of ₹2.50 crore per MW goes to utility-scale solar with four-hour storage of 5 MW or more, and to standalone batteries charged only from solar, that sell to a DISCOM or UPPCL (clause 11.2). On our reading, a battery behind a site's meter does not qualify. The policy runs five years or until replaced. We found no UP rule tying storage to rooftop or captive solar.


What it means for you

  • If you run a site: In Noida, Greater Noida or Ghaziabad, check the generator's nameplate against the GRAP table first. A factory can earn back a battery on the time-of-day swing; an office, hospital or mall on HV-1 earns it on diesel saved and on fixed charges above the 75% floor.

  • If you make or install batteries: Ask for the tariff category, the contracted demand and last winter's generator log first. An HV-1 quote promising time-of-day savings will fail the first bill check.

  • If you lend or lease: Underwrite UP commercial deals on diesel displaced and demand trimmed, and factory deals on the 15% swing, which any year's order can change.


The number to know

₹2.13 per kVAh: the peak to off-peak gap for an urban HV-2 factory at up to 11 kV; for HV-1 commercial sites it is zero. Our calculation: ₹7.10 × 1.15 = ₹8.165; ₹7.10 × 0.85 = ₹6.035; difference ₹2.13.


What to do now

  1. Find your tariff category, contracted demand and supply voltage on your bill, and compare your recorded maximum demand with 75% of the contract.

  2. In an NCR district, list every diesel set by size, fuel mode and emission standard, and match it to the GRAP table above.

  3. Pull last winter's generator log and count the hours a battery of two to four hours could have covered.


What we don't know yet

  • Whether UPERC will add time-of-day rates for commercial users, as the 2023 national rule asked.

  • Whether UPERC will set a diesel backup timeline under Rule 10(6).

  • Noida Power Company's 2026-27 rates for business users in Greater Noida.


Questions people ask

Q: Does GRAP apply in Noida and Ghaziabad? A: Yes. GRAP covers the whole NCR, including Gautam Buddh Nagar and Ghaziabad. Stage I, with the generator rules, has applied since 21 October 2026.


Q: Can I run a diesel generator in Noida during GRAP? A: It depends on the set. Gas sets and sets up to 800 kW built to the 2022 standard have no restriction; older diesel sets need dual-fuel mode or a certified retrofit, by size. The emergency-service exception covers only the smallest sets.


Q: Do commercial buildings in UP pay time-of-day electricity rates? A: Not under the 2026-27 schedule. Only urban LMV-6 and HV-2 industrial users do.


Sources


Keep reading


Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.