CEA draft: new solar and wind plants may need batteries from July 2027

Updated: 3 days ago
From our archive: we wrote this note after the week shown above, as part of our back catalogue. For anything newer, see the latest posts in this section.
A draft issued by the Central Electricity Authority (CEA) on 3 September 2026 would require new ground-mounted solar and onshore wind plants commissioned after 1 July 2027 to include batteries of at least 10% of plant capacity for two hours, rising to four hours from July 2029. It's a draft, and comments closed on 15 October after the CEA extended its 4 October deadline. If you're planning a captive or open access solar contract that starts after mid-2027, ask now whether it would be caught, and who pays.
The Storage Brief, week of 7 September 2026
What changed
The CEA issued the draft Second Amendment to its technical standards for building electrical plants and lines on 3 September 2026, under Section 177 of the Electricity Act. It would insert a new clause, Regulation 106B(20), into the 2022 standards.
Ground-mounted solar and onshore wind projects commissioned after 1 July 2027 would need storage at the same site of at least two hours, sized at no less than 10% of installed capacity. For projects commissioned after 1 July 2029 and up to 30 June 2031, the minimum rises to four hours. At least 15% of inverters in new renewable plants would need grid-forming control, and so would all battery power conversion systems. The CEA may change these percentages by notification.
Comments were first due by 4 October 2026. The CEA later extended the deadline to 15 October 2026.
Why it matters
For a business that buys solar power, the first question is whether it applies at all. The draft's storage clause names ground-mounted solar and onshore wind plants. It doesn't say whether captive plants, open access projects or group captive arrangements are covered or exempt, and rooftop solar isn't mentioned. Until the final text settles that, a ground-mounted solar contract starting after 1 July 2027 carries an open cost question.
Take a cement plant that signs for power from a 20 MW ground-mounted solar park due in late 2027 (an example). If the draft applies, the developer must add 4 MWh of batteries (our calculation: 20 MW × 10% = 2 MW; 2 MW × 2 hours = 4 MWh). That cost may show up in the cement plant's tariff.
But those batteries sit at the solar park, behind the park's own connection. When the grid fails at the cement plant, they don't keep its equipment running. A mandate at the source shifts when green power is delivered; a battery at your site gives you backup.
What it means for you
Sites: Ask your solar developer whether projects due after July 2027 would fall under the draft and how they'd price it. Keep that separate from your own backup plan.
Battery makers: If the rule is finalised, expect large demand for plant-side batteries from 2027, which could compete with commercial orders for cells and crews.
Lenders: For solar projects commissioning after July 2027, ask developers to show a case with and without the storage requirement.
The number
1 MWh: the storage a 5 MW ground-mounted solar plant would need in the first phase, if the draft applies to it. Source: our calculation, 5 MW × 10% = 0.5 MW, and 0.5 MW × 2 hours = 1 MWh.
What to do now
List any captive or open access solar contracts under negotiation with start dates after 1 July 2027.
Ask each developer in writing whether the CEA draft would apply and how the cost would be shared.
Comments closed on 15 October 2026. Watch for the final notification, which would take effect on publication in the Gazette.
What we don't know yet
Whether captive, group captive and open access projects will be covered or exempt in the final rule.
Whether the final rule will keep the 10% and two-hour figures.
How projects already contracted but commissioning after July 2027 will be treated.
Questions we get asked
Q: Is battery storage mandatory for new solar projects in India? A: Not yet. It's a draft, and comments closed on 15 October 2026 after an extension. If finalised, it would apply to projects commissioned after 1 July 2027.
Q: Does the CEA storage rule cover rooftop solar on my factory? A: The draft's storage clause names ground-mounted solar and onshore wind. Rooftop isn't mentioned, so check the final notified text.
Q: Will the solar plant's battery give my site backup during a power cut? A: No. A battery at a distant solar plant shapes when power reaches the grid. Backup during an outage needs storage at your own premises.
Key facts
Issued by: Central Electricity Authority
Date: 3 September 2026; comments due 4 October 2026, extended to 15 October 2026
Status: draft
Applies to: new ground-mounted solar and onshore wind plants
Takes effect: projects commissioned after 1 July 2027 (two hours at 10% of capacity); four hours for projects commissioned after 1 July 2029 and up to 30 June 2031, if finalised
What it means for business batteries: plant-side storage may raise green power tariffs but gives a site no backup of its own.
Sources
Draft CEA (Technical Standards for Construction of Electrical Plants and Electric Lines) Second Amendment Regulations, 2026. Central Electricity Authority, 3 September 2026.
Extension of the last date for public comments. Central Electricity Authority, 2026.
India's CEA proposes mandatory storage for new solar, wind projects from 2027. PV Tech, 4 September 2026.
CEA proposes 15 percent grid forming inverters, 10 percent ESS for new RE projects from July 2027. Energética India, 3 September 2026.
New solar, wind plants may need battery storage from 2027. DT Next, 5 September 2026.
Keep reading
Newer in Rules: When is a storage project 'commissioned'? CERC's draft grid code
Earlier in Rules: New wind and solar lose softer deviation rules: where batteries fit
Check your site: Which battery and diesel rules apply to my site? A quick check for India
Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.
