When is a storage project 'commissioned'? CERC's draft grid code

Updated: 3 days ago
From our archive: we wrote this note after the week shown above, as part of our back catalogue. For anything newer, see the latest posts in this section.
The Central Electricity Regulatory Commission (CERC) has proposed changes to the Indian Electricity Grid Code that set out how storage projects run trial operations, and when they may sell power before commercial operation. The draft, issued on 21 September 2026, covers grid-connected storage, not batteries behind a business meter. But it answers the question every storage contract has to answer: what counts as "commissioned", and when does payment start?
The Storage Brief, week of 14 September 2026
What changed
CERC issued the draft CERC (Indian Electricity Grid Code) (Second Amendment) Regulations, 2026 with a public notice dated 21 September 2026, just after this week; nothing stronger fell inside the week itself.
Under the draft, standalone energy storage would generally run trials at a minimum of 50 MW. Projects of 250 MW and above could run trials in instalments of at least 50 MW, with no limit on the number of instalments, as Indian Infrastructure reported. Power injected before commercial operation ("infirm power") could be scheduled only after a successful trial run. It's a draft. Comments were first due by 21 October; CERC has extended that to 2 November and set an online public hearing for 4 November 2026.
Why it matters
For a lender, the commissioning date is the hinge. Before it, a project is construction risk. After it, a project is a stream of payments. Letting a large battery prove itself in 50 MW slices means part of it can start earning while the rest is still being finished. Capital sits idle for less time, and the lender sees evidence of performance earlier.
The same logic applies at a hospital or a factory, on a smaller scale. A business battery order needs a written handover test: what the system must deliver, on what day, before the monthly plan starts and the maker is paid.
Take a hospital in Lucknow putting a battery on a monthly plan (an example). Its handover test might say the system must carry 200 kW of critical load for two hours, which means at least 400 kWh of usable energy (our calculation: 200 kW × 2 hours), and pick up that load the moment the grid fails. The facility head and the maker both sign the result. Only then does the first monthly payment fall due.
The grid code is moving towards milestones that can be tested and signed. Business contracts should too. The draft also adds congestion charges when power flows exceed total transfer capability, and limits grid access for entities that default on statutory charges such as deviation settlement. The grid is getting stricter about paying for what you use.
What it means for you
Sites: Nothing changes behind your meter. But ask any battery supplier how they define handover, and what the system must show on that day.
Battery makers: If you also bid on grid projects, instalment trials can bring revenue forward. For business orders, put a handover test in the quote now, because lenders will ask for one.
Lenders: Commissioning in instalments changes drawdown and repayment timing. Tie loan milestones to completed trial runs rather than delivery alone.
The number
10: the most 50 MW trial instalments a 500 MW storage project would need under the draft. Source: our calculation, 500 MW ÷ 50 MW minimum instalment = 10.
What to do now
Read the draft on CERC's website before you rely on any clause. Comments close on 2 November 2026.
If you buy or sell business batteries, write down the handover test: power, hours of discharge, response time on a grid failure, and who signs.
If you lend, list storage loans whose milestones depend on "commercial operation" and check how each contract defines it.
What we don't know yet
When a final version will be notified, and what changes after the 4 November hearing.
Whether state commissions will copy instalment-style trials for storage on distribution networks.
How the proposed congestion charges will treat storage that charges during crowded hours.
Questions we get asked
Q: Does the CERC grid code apply to a battery at my factory? A: No. The draft covers projects connected to the inter-state grid. A battery behind your meter follows your state commission's rules and the Central Electricity Authority's safety regulations.
Q: What is infirm power in a storage project? A: Power a project puts into the grid before it's declared commercially operational. The draft would let storage schedule it only after a successful trial run, offered first to contracted buyers, where the contract is silent, with at least seven days' notice.
Key facts
Document: Draft CERC (Indian Electricity Grid Code) (Second Amendment) Regulations, 2026
Issued by: Central Electricity Regulatory Commission
Date: public notice dated 21 September 2026; comments due 2 November 2026 (extended); public hearing 4 November 2026
Status: draft
Applies to: storage and other entities connected to the inter-state grid
What it means for business batteries: no direct effect behind the meter, but business contracts should also tie payment to a signed handover test.
Sources
Public notice on the draft IEGC (Second Amendment) Regulations, 2026. Central Electricity Regulatory Commission, 21 September 2026.
Notice of public hearing and extended comment date. Central Electricity Regulatory Commission, 22 October 2026.
CERC issues draft CERC (Indian Electricity Grid Code) (Second Amendment) Regulations, 2026. Indian Infrastructure, 23 September 2026.
CERC proposes congestion charges, new commissioning rules for energy storage. Mercom India, 22 September 2026.
Keep reading
Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.