Chhattisgarh draft: solar above 5 MW may need a battery from 2027

Writer: Vaultus
Vaultus
Sep 21
4 min read

Updated: 3 days ago

From our archive: we wrote this note after the week shown above, as part of our back catalogue. For anything newer, see the latest posts in this section.


Chhattisgarh's electricity regulator proposed on 22 September 2026 that new distributed renewable projects above 5 MW, commissioned on or after 1 April 2027, install battery storage of at least 5% of their capacity for two hours. Captive plants larger than the consumer's contract demand would need storage equal to 20% of the excess. It's a draft, and comments were due by 13 October 2026.


The Storage Brief, week of 21 September 2026


What changed

On 22 September 2026, the Chhattisgarh State Electricity Regulatory Commission (CSERC) released the draft Grid Interactive Distributed Renewable Energy Sources (Third Amendment) Regulations, 2026.


Beyond the storage rule, it reworks banking for green open access projects commissioned on or after 1 April 2027. Banking would move to a monthly cycle, capped at 30% of monthly consumption from the distribution company, with an 8% in-kind charge. Withdrawing banked units between 09:00 and 17:00 would carry no charge, 23:00 to 09:00 would carry 10%, and 17:00 to 23:00 would carry 30%, both in units. The CSERC public notice set comments by 13 October 2026 and a hearing on 14 October.


Why it matters

The draft puts a price on time. Daytime solar that's banked and drawn in the evening would carry the highest charge. Power a prosumer puts into the grid between 19:00 and 24:00 would earn ₹8 per kWh, settled in the billing period, while unused banked surplus would be bought at ₹1.94 per kWh. Read together, these rules make the battery the tool that turns cheap daytime units into valuable evening ones. The regulator doesn't have to subsidise the battery. It only has to price the hours.


The captive rule matters for factories. Take a factory in Raipur with 8 MW of contract demand that plans a 10 MW captive solar plant for 2027 (an example). The draft stacks the captive requirement on top of the 5% rule, both for at least two hours, and its worked illustration applies the 5% up to contract demand and the 20% above it. That gives 1.6 MWh (our calculation: 8 MW × 5% × 2 hours = 0.8 MWh; 2 MW × 20% × 2 hours = 0.8 MWh). An 8 MW plant would need only 0.8 MWh. The rule nudges owners to size plants closer to their load, or to plan the battery from day one.


On the other side of the ledger, the draft proposes a seven-year waiver of transmission charges, wheeling charges, cross-subsidy surcharge and load despatch charges for new projects above 5 MW commissioned on or after 1 April 2027. A battery requirement and a charges waiver arriving together move the project budget in both directions.


What it means for you

  • Sites: If you plan captive or open access solar in Chhattisgarh for 2027, model it with the battery now, sized to the draft's rules, and use your evening load profile.

  • Battery makers: Two-hour systems for distributed solar plants above 5 MW would become a defined product category. Prepare a standard offer.

  • Lenders: A mandated battery is part of the project, not an optional add-on. Underwrite solar and storage as one cash flow.


The number

4.1 times: what an evening prosumer unit would earn compared with an unused banked surplus unit under the draft. Source: our calculation, ₹8.00 ÷ ₹1.94 = 4.1.


What to do now

  1. Get the draft from CSERC's website and read the definitions of "distributed renewable energy" and "captive" before assuming you're covered.

  2. Pull your contract demand and your hourly load for the last year, and check how much of any planned solar would sit above contract demand.

  3. Ask two battery makers for a two-hour quote at 5% of your planned solar capacity.


What we don't know yet

  • The final text, and whether the 5% and 20% figures survive comments.

  • Whether the 5% covers a captive plant's full capacity, as the clause reads, or only the part up to contract demand, as the illustration has it.

  • What came out of the 14 October hearing, and when the final rule will be notified.


Questions we get asked

Q: Does Chhattisgarh's battery rule apply to my existing solar plant? A: Under the draft, the mandate applies to new projects above 5 MW reaching commercial operation on or after 1 April 2027. Existing plants may add co-located storage as a separate project, under the rules in force when it starts operating.


Q: Can a behind-the-meter solar and battery system bank power with the power distribution company (DISCOM) in Chhattisgarh? A: Not under the draft, if it's grid-connected behind the meter (co-located, with a reverse power protection relay). Power from a distant plant can be banked with the licensee or a battery at your premises.


Key facts

  • Document: Draft Chhattisgarh State Electricity Regulatory Commission (Grid Interactive Distributed Renewable Energy Sources) (Third Amendment) Regulations, 2026

  • Issued by: Chhattisgarh State Electricity Regulatory Commission

  • Date: 22 September 2026; comments due 13 October 2026, public hearing 14 October 2026

  • Status: draft

  • Applies to: new distributed renewable projects above 5 MW, captive plants larger than contract demand, and green open access banking

  • Takes effect: on notification in the state gazette, if finalised; the storage and new banking terms apply to projects commissioned on or after 1 April 2027

  • What it means for business batteries: larger captive and open access solar in Chhattisgarh would need a two-hour battery, and evening banking would cost more.


Sources


Keep reading





Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.