On 5 October 2026 the Central Electricity Authority (CEA) asked for comments on a draft list of the standards that apply under its electrical safety regulations, including the new chapter on battery energy storage that takes effect on 1 April 2027. Comments are due by 15 November 2026. For battery makers, this list is where "comply with relevant standards" turns into a checklist.


The Storage Brief, week of 5 October 2026


What changed

The CEA posted a notice on 5 October 2026 seeking public comments on a draft List of Relevant Standards applicable under the CEA (Measures relating to Safety and Electric Supply) Regulations, 2023 and their amendments.


The list is issued under Regulation 137, which asks the CEA to publish it within three months of the 2026 amendment taking effect. It pairs each clause with Indian Standards and international standards from the IEC, NFPA, IEEE and UL. For battery storage, the draft maps the new battery clauses one by one: walk-in containers (Regulation 122C) to IS 17092 and UL 9540A, spacing between enclosures and buildings (122D) to NFPA 855, automatic fire suppression in every battery container (122F) to NFPA 855, UL 9540A and IEC 62619, and electrolyte spill containment (122G). UL 9540, UL 1973 and the IEC 62933 series also appear. Comments close on 15 November 2026. The list sits under the 2026 amendment that added Chapter XA on battery storage, effective 1 April 2027.


Why it matters

Ask a hospital's fire officer, an insurer or a lender about a battery and the first question is the same: which standard it meets. A single CEA list gives everyone the same reference. A maker with test reports against the listed standards can answer in one line. A maker without them may find financed orders stall at approval, because the person signing off now has a document to check against.


There's also a deadline hiding in the amendment. As reported in April, Chapter XA requires every battery installation to undergo an independent third-party fire safety audit within three months of the rules taking effect, with the report sent to the Electrical Inspector. It also requires designs that stay safe after two independent failures. Chapter XA applies to installations above 650 volts. Systems at or below 650 volts must comply with the relevant standards, which is what this list will define.


Take a hospital in Pune that installed a battery in 2026 (an example). If its system runs above 650 volts, Chapter XA applies in full and the fire audit report is due by the end of June 2027 (our calculation: 1 April 2027 plus three months). If it runs at or below 650 volts, the hospital's question becomes which standards on the final list the system was tested against. Either way, the facility head needs the voltage figures and the test reports in one file before April.


What it means for you

  • Sites: Find out your battery's operating voltage and ask your maker which listed standards it was tested against.

  • Battery makers: Map every product to the draft list now, find the gaps, and send comments by 15 November if a standard is unclear or unworkable for small systems.

  • Lenders: Add "tested to the CEA list" to your approval checklist, and budget for the 2027 fire audit in the contract.


The number

650 volts: the line that decides whether Chapter XA's provisions apply in full or a system must meet the relevant standards on the list. Source: Energetica India, 14 April 2026.


What to do now

  1. Download the draft list from the CEA's "What's New" page and read the sections on renewables and emerging technologies.

  2. Battery makers: build a one-page matrix of each product against each listed battery standard, with test report numbers.

  3. Sites with batteries already installed: if Chapter XA covers your system, plan for a third-party fire safety audit by the end of June 2027. Our calculation: 1 April 2027 plus three months.


What we don't know yet

  • Which specific standard numbers will apply to systems at or below 650 volts once the list is final.

  • How the third-party fire audit will work for small sites, and who will be accepted as an auditor.

  • Whether test reports from labs abroad will be accepted against the listed standards.


Questions we get asked

Q: Are the CEA battery safety rules already law? A: The battery chapter (Chapter XA) has been notified and takes effect on 1 April 2027. The list of relevant standards is a draft, open for comments until 15 November 2026.


Q: My battery system runs at 400 volts AC. Which CEA rules apply? A: As reported, Chapter XA's provisions apply above 650 volts, and systems at or below must comply with the relevant standards. Batteries also run at a DC voltage, so ask your maker for both figures and check the notified text.


Key facts


Sources


Keep reading





Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.