A business site in Madhya Pradesh faces three state rules beyond the national ones: a time-of-day tariff, a billing-demand floor and a cap on banking green power. The tariff matters most. HT users and LT business users above 10 kW pay 20% more for energy in the morning and evening peaks and 20% less in solar hours, a gap of ₹3.26 a unit for an HT office, hotel or hospital on 11 kV (our calculation).


The Storage Brief, state guide, updated 31 October 2026


The rules at a glance

  • Time-of-day tariff (in force). 20% on the energy charge from 6 am to 9 am and 5 pm to 10 pm, 20% off from 9 am to 5 pm, for HT users and LT business users above 10 kW. Set in the FY 2026-27 tariff order.

  • Billing-demand floor (in force). HT users pay fixed charges on their actual maximum kVA or 90% of contract demand, whichever is higher. Same order.

  • Banking cap for green open access (in force). Monthly banking is capped at 30% of what the consumer draws from the DISCOM, Mercom reported.

  • Renewable Energy Policy 2025 (policy). Targets 6,000 MW of storage by FY 2030 and 12,000 MW by FY 2035, the Free Press Journal reported.


Your electricity bill

The Madhya Pradesh Electricity Regulatory Commission (MPERC) passed the order on 26 March 2026 for the Paschim, Madhya and Poorv Kshetra DISCOMs, allowing a 4.80% rise against the 10.19% sought.


For HT business users the time-of-day rule works on the energy charge only; the order says it "shall not be applicable on Fixed charges". Nights from 10 pm to 6 am earn a 7.5% rebate in April, May and October to March.


The HV-3.2 non-industrial category covers "Offices, Hotels, Hospitals, Institutions etc." At 11 kV it pays ₹373 per kVA a month and 815 paise a unit, or 725 paise above 50% load factor. Industry pays ₹409 and 779 paise.


Take an 11 kV hospital with 500 kVA contract demand whose battery moves 1,000 units a day out of the evening peak (an example). Peak energy costs ₹9.78 and solar-hour energy ₹6.52 (our calculation: ₹8.15 × 1.2 and ₹8.15 × 0.8). Allowing for 10% losses, it buys 1,111 units at ₹6.52, or ₹7,244, to avoid 1,000 peak units at ₹9.78, or ₹9,780. That leaves about ₹2,536 a day, or ₹76,080 over 30 days (our calculation, before fuel surcharges and duty).


Under the 90% floor the hospital pays fixed charges on at least 450 kVA, or ₹1,67,850 a month (our calculation: 450 × ₹373). Trimming the peak saves ₹373 a month for each kVA cut, but only down to that 450 kVA line. Below it, contract demand has to come down too.


Diesel backup

The national five-year rule on moving diesel backup to cleaner options applies. We could not find an MPERC timeline under it, or a state pollution board direction on diesel sets at business sites. No Madhya Pradesh district is in the National Capital Region, so the Delhi-NCR winter curbs don't apply.


A diesel unit costs about ₹34 at ₹95 a litre and 2.8 units a litre (an example; our calculation: ₹95 ÷ 2.8). The dearest HV-3.2 grid unit is ₹9.78.


Solar and storage

M.P. Power Management Company, the state's power buyer, tendered 750 MW/1,500 MWh in January 2026, 282.5 MW/1,130 MWh in May and 625 MW/1,250 MWh in July. The July tender asks for two full cycles a day under 12-year contracts, with viability gap funding of up to ₹18 lakh per MWh, SolarQuarter reported. In October MPERC adopted ₹1,92,000 per MW a month for a 125 MW/250 MWh project, Mercom reported. Rewa Ultra Mega Solar's Morena solar-plus-storage auction cleared at ₹2.70 and ₹2.764 a unit, Energetica reported.


MPERC's net metering regulations cover all consumer categories, but a site on net or gross metering can't also use open access, Energetica reported. Banked green power follows the same peak and off-peak periods as the tariff. We found no state capital subsidy for business batteries.


What it means for you

  • If you run a site: Your evening load is where the money is: each unit moved into solar hours is worth ₹3.26 on HV-3.2 at 11 kV.

  • If you make or install batteries: Size to the evening peak and pair it with a contract-demand cut, or the 90% floor swallows the fixed-charge saving.

  • If you lend or lease: The spread is set in a public order each year, and the state's own storage contracts run 12 years. Both help a site's repayment case.


The number to know

₹3.26 a unit: the gap between evening-peak and solar-hour energy for an HT office, hotel or hospital on 11 kV at up to 50% load factor. Our calculation: ₹8.15 × 1.2 minus ₹8.15 × 0.8, from the MPERC FY 2026-27 schedule.


What to do now

  1. Pull 12 months of HT bills and note units billed in peak, solar and night slots.

  2. Compare contract demand with actual maximum demand. If you pay on the 90% floor, plan any demand cut with the battery.

  3. If you buy open access solar, check how much midday surplus falls above the 30% banking cap.


What we don't know yet

  • Whether MPERC will set a diesel replacement timeline under the national rule.

  • The full banking procedure, including charges and when banked units can be drawn.

  • Whether the 2025 policy's incentives reach batteries at sites.


Questions people ask

Q: Does Madhya Pradesh charge more for electricity in the evening? A: Yes. HT users and LT business users above 10 kW pay 20% more from 6 am to 9 am and 5 pm to 10 pm, and 20% less from 9 am to 5 pm.


Q: Is there a subsidy for business batteries in Madhya Pradesh? A: We found no capital subsidy for batteries at business sites. Check eligibility under the 2025 policy with the state's renewable energy department.


Sources


Keep reading





Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.