A business site in Telangana faces four state rules beyond the national ones, and the biggest is the time-of-day tariff on high-tension (HT) bills. Since 1 April 2026, HT sites pay ₹1.50 a unit extra from 6 to 10 am and 6 to 10 pm, and ₹0.50 less from 10 am to 6 pm. With no night rebate, the cheapest power is now at midday.
The Storage Brief, state guide, updated 31 October 2026
The rules at a glance
Time-of-day tariff, FY 2026-27 (in force). Peak surcharge and midday rebate for HT industry, HT commercial, airports, stations and EV charging. TGSPDCL tariff schedule.
Rooftop solar regulation, 2025 (notified). Commercial and industrial sites can install rooftop solar up to 80% of sanctioned load, on net, gross or virtual net metering. Energetica India report.
Open access regulation, 2024 (in force). Sites with a load of 100 kW or more can buy green power through open access. India Environment Portal.
Clean and Green Energy Policy, 2025 (policy, G.O.Ms.No.2 of 11 January 2025). Plans 3,388 MW of battery storage by FY 2029-30 and 5,450 MW by FY 2034-35, with incentives for storage projects and battery factories. Energy Department order.
Your electricity bill
HT-II(A) Others, the HT category outside industry, pays ₹8.80 a unit at 11 kV (unchanged from FY 2025-26), ₹8.00 at 33 kV and ₹7.80 at 132 kV, plus ₹500 per kVA a month. The time-of-day terms changed:
6 am to 10 am, 6 pm to 10 pm: FY 2025-26: plus ₹1.00; FY 2026-27: plus ₹1.50
10 am to 6 pm: FY 2025-26: normal; FY 2026-27: less ₹0.50
10 pm to 6 am: FY 2025-26: less ₹1.50; FY 2026-27: normal
Source: the FY 2025-26 and FY 2026-27 schedules. In April 2026 the commission refused a plea to restore the night rebate and said peak or solar-hour changes "can be made only through a tariff order" (Mercom, 6 April 2026).
Take a hospital on 11 kV supply (an example). Peak power costs ₹10.30 a unit and midday power ₹8.30 (our calculation: 8.80 + 1.50; 8.80 − 0.50). A 500 kWh battery charged at midday and run in the evening peak saves about ₹539 a day (our calculation: 500 × ₹10.30 = ₹5,150 avoided, less 555.6 kWh (500 ÷ 0.9, at 90% round-trip efficiency) bought at ₹8.30 = ₹4,611). The demand charge can matter more: each kVA cut from billed demand is worth ₹500 a month, so 100 kVA is ₹50,000 (our calculation: 100 × ₹500). Check how your DISCOM sets billed demand first.
Diesel backup
We found no Telangana commission timeline under Rule 10(6) of the consumer rules, so the national five-year push to cleaner backup applies. Diesel stays dear: at ₹95 a litre and 2.8 units a litre, a unit costs about ₹34 (an example; our calculation: 95 ÷ 2.8), against about ₹9.22 for a battery charged at midday (our calculation: 8.30 ÷ 0.9).
Solar and storage
The rooftop regulation was issued on 15 November 2025, according to trade reports. Net and gross metered sites are exempt from banking, wheeling and cross-subsidy charges, Energetica India reported. Green open access buyers can bank up to 30% of monthly use for one month, at a charge of 8% of the energy banked (Energetica India, 12 July 2024). Neither rule asks for storage alongside solar.
The policy gives storage projects deemed non-agricultural land status, full stamp duty reimbursement on land and exemption from pollution board consent. It also says the DISCOMs will use time-of-day tariffs to shift demand into solar hours (policy).
The state is already buying grid-scale storage. The commission approved a 1,500 MWh standalone project at the Maheshwaram and Choutuppal substations, tendered with TGGENCO as nodal agency: four-hour batteries on 15-year contracts at ₹2.98 lakh and ₹3.14 lakh per MW a month (SolarQuarter, 25 June 2026). In September 2026 TGNPDCL tendered a 1 MW / 4 MWh battery at a Karimnagar substation (SolarQuarter).
What it means for you
If you run a site: Move flexible load such as chilling and pumping into 10 am to 6 pm, and size any battery around the evening peak and your demand charge.
If you make or install batteries: A midday-charged battery here pays mostly through demand charges and diesel, so lead with those. Battery factories get a 20% capital subsidy, capped at ₹30 crore a plant, until the state reaches 5,000 MWh.
If you lend or lease: The time-of-day terms changed in April 2026 and can change again. Underwrite on the current schedule and test a narrower gap.
The number to know
₹2.00 per unit: the gap between peak and midday power for HT-II(A) at 11 kV in FY 2026-27. Our calculation: (₹8.80 + ₹1.50) − (₹8.80 − ₹0.50).
What to do now
Pull a year of HT bills and split units by the three time blocks.
Find your billed demand and the hours it was set.
Get a battery quote sized to your evening peak and generator hours; compare it with a year of diesel spend.
What we don't know yet
Whether the FY 2027-28 order will adopt the national 1.2 times peak and 20% solar-hour discount. Today's peak is 1.17 times normal (our calculation: 10.30 ÷ 8.80); the national ratios would widen the gap to ₹3.52 (our calculation: 10.56 − 7.04).
Whether the policy's storage incentives, written for projects that sell power, will reach batteries behind a site's meter.
Questions people ask
Q: Do LT commercial shops and offices in Telangana pay time-of-day rates? A: Not under the FY 2026-27 schedule, which lists time-of-day rates only for HT categories.
Q: Is there still a night rebate for HT industry in Telangana? A: No. Since 1 April 2026, 10 pm to 6 am is billed at the normal rate.
Sources
Retail Supply Tariff schedule, FY 2026-27. TGERC, published by TGSPDCL, 2026.
Retail Supply Tariff schedule, FY 2025-26. TGERC, published by TGSPDCL, 2025.
Telangana Clean and Green Energy Policy, 2025 (G.O.Ms.No.2). Energy Department, Government of Telangana, 11 January 2025.
TSERC (Terms and Conditions of Open Access) Regulation, 2024. India Environment Portal, 14 March 2024.
Telangana regulator rejects plea to restore night-time tariff rebate. Mercom India, 6 April 2026.
Telangana unveils 2025 rooftop solar reforms. Energetica India, 22 November 2025.
Telangana unveils new regulations for green energy open access. Energetica India, 12 July 2024.
TGERC approves Telangana's first 1,500 MWh battery storage project. SolarQuarter, 25 June 2026.
Keep reading
Next state guide: Uttar Pradesh: battery, diesel and solar rules for business sites
Check your site: Which battery and diesel rules apply to my site? A quick check for India
Where tariffs are heading: Business power tariffs in 2026-27: which way are they moving?
Vaultus puts business batteries on a monthly plan. The battery maker installs and maintains the system, the site pays monthly, and the contract sets how much backup it gets. Send your last 12 months of electricity bills and diesel records to contact@vaultus.io, or run your own numbers with the site calculator.